End User Project Name Order Date 수량(Set) 중량(Ton) 품명 크기(mm) 재질 Amount Remark
ECOPRO-HN
Pyeongtaek Air Prevention Facility
22.10 ~ 23.02 3 SETS Pyeongtaek Godeok
SEBANG-TECH
Pyeongtaek P3 PH3 N-SUP
Machine room piping/steel fabrication
22.08 ~ 22.11 14,500 D/I Pyeongtaek Godeok
SEBANG-TECH
Pyeongtaek P3 PH2 S-SUP
Manufacture of piping in machine room
22.07 ~ 22.11 29,500 D/I Pyeongtaek Godeok
SEBO MEC
SDC 8-2 Line Fire Extinguishing Piping
SP-HEAD Installation Construction
22.07 ~ 23.03 16,390 SETS Asan Tangjeong
SEBANG-TECH
Pyeongtaek P3 PH34F OAC
Fabrication of MEGA MODULE
22.05 ~ 22.12 850 TONS / 47,500 D/I Pyeongtaek Godeok
ECOPRO-HN
Pyeongtaek Air Prevention Facility
Manufacturing and Installing RCS
22.05 ~ 22.12 10 SETS Pyeongtaek Godeok
SEBANG-TECH
Pyeongtaek P3 PH24F OAC
Fabrication of By-Pass Piping
22.04 ~ 22.07 26,800 D/I Pyeongtaek Godeok
SEIL ENS
Pyeongtaek P3 PH21FSF Fabrication of Module and PCW Piping
22.04 ~ 22.06 75 TONS / 12,400 D/I Pyeongtaek Godeok
SEBANG-TECH
Pyeongtaek P3 PH2 PCW Piping Manufacture
22.04 ~ 22.06 14,500 D/I Pyeongtaek Godeok
SEBANG-TECH
Production of P3 Ph2 PCW MR rack / Reinforcement of suspension crane
22.04 ~ 22.06 42 TONS Pyeongtaek Godeok
SEBO MEC
Asan Retrofit Site
UT1 copper pipe rack repair
21.11 ~ 22.04 70 TONS Asan Tangjeong
SEIL ENS
Pyeongtaek P3-PH1-1FSF
Fabrication of modules and spools
21.11 ~ 21.12 65 TONS / 12,500 D/I Pyeongtaek Godeok
SEBO MEC
A4-2L conversion workM
(firefighting equipment construction)
21.10 ~ 22.06 308,600 D/I Pyeongtaek Godeok
SEBANG-TECH
Pyeongtaek P3-PH1-1F
OAC MEGA MODULE Fabrication
21.10 ~ 22.01 750 TONS / 46,500 D/I Pyeongtaek Godeok
HHI
DSO HHI
2020 1 SET / 4 TONS SA516-70
SKEC
JAC Singapore
2020 15 SETS / 54 TONS SA516-70
LANXESS
BTR Singapore
2020 3 SETS / 2.5 TONS SA312-304
CB&I
PNG EPC4
2020 5 SETS / 53 TONS SA106-B
Total E&P Nigeria Ltd.
Egina FPSO
2019 39 SETS / 455 TONS SA240-316L
SA516-70N+S3+S5+316LS.S
YNCC
YNCC C5 Separation
2019 10 SETS / 163 TONS SA516-70N
Alstom
Wolf Hollow
2019 6 SETS / 116 TONS SA299-B
SABIC
Yansab Olefin PJT - Spare , Heat Exchanger
2019 1 SET / 19 TONS SA516-70
DOW CHEMICAL
Gulfstream PUI Project
2019 3 SETS / 51 TONS SA516-70
DOW CHEMICAL
LHC-9
2019 9 SETS / 179 TONS SA516-70(N)
BP Group
SCPX Project
2019 8 SETS / 524 TONS SA537 CL/2
Technip France
Yamal LNG
2019 24 SETS / 1748 TONS SA516-70N+S5
SA240-304L
POSCO
POSCO SNG PJT
2019 2 SETS / 173 TONS SA516-70N
Chevron
USGC Petrochemicals
2019 120 SETS / 2031 TONS SA516-70
SA516-70N+S5+304 CLAD
KBR
Agrium lone Star Project
2019 25 SETS / 151 TONS SA516-70 / A266
SA516-70 / SA387-22
SAUDI ARAMCO
Shaybah Increase Gas Handling, Capacity Project
2018 14 SETS / 103 TONS A516-70+HIC